Capacity is a model-mix question
The honest answer to "how many dining armchair a day" is "of which model". A simple frame runs fast; an upholstered dining armchair with a deep finish takes the same bench hours as two simple ones. Quotations are planned against the mix, not against an average.
Packing runs 0.14 to 0.20 m³ for two with protective arm covers, because an arm is the easiest thing to damage in transit and the most expensive to replace. MOQ is 6 pieces per model.
What the mix looks like right now
The catalogue lists 253 models in this category: 87% on a solid or wood frame and 13% with an upholstered or soft cover.
The most common order quantity in this category is 6 pcs (207 models ship at that level).
| Factor | Effect | Planning note |
|---|---|---|
| Model complexity | Frame vs upholstered | Sets bench hours |
| Finish system | Coat count | Booth time per piece |
| Season | CNY and peaks | Lead time +/- weeks |
| Mix | Simple vs detailed dining armchairs | Bottleneck location |
| Surge | Overtime, quoted | Never free |
Capacity factors
The bottleneck moves with the order
Finishing and upholstery are the usual limits; a plain-frame dining armchair run is limited by machining instead. Knowing where the bottleneck sits is how a promised date is built.
The arm is the expensive machining job in this category. It is a shaped, tapered component that has to meet the back post at a fixed angle, and that tenon is cut on the tenoner rather than by hand — a hand-cut arm joint is the failure we get called about.
Seasonality is real
Pre-Chinese-New-Year months run at full stretch and lead times stretch with them; post-holiday months have slack. Buyers who plan around the calendar get better dates than buyers who plan around hope.
Packing runs 0.14 to 0.20 m³ for two with protective arm covers, because an arm is the easiest thing to damage in transit and the most expensive to replace. MOQ is 6 pieces per model.
What surge capacity actually costs
Yes, the line can sprint - with overtime and with finish quality held by inspection rather than by schedule. It is available, it is quoted, and it is never free.
An armchair is tested for a downward and a sideways load on the arm itself, not only for seat and back fatigue. That arm load test is what separates a hospitality-grade armchair from a domestic one.
Reference
Questions
What is your daily output for dining armchairs?
It depends on the model mix; quotations carry a production plan with the bottleneck named, not a round number.
Can you hold a peak-season date?
Dates are promised against the calendar, not against hope - peak-season orders are booked with the stretch priced in.
Why did my simple model run late?
If the mix that week was upholstery-heavy, the simple frames queue behind the booth. The plan, not the promise, is what to read.
How early should I book a big wooden dining armchairs order?
Ahead of the pre-holiday stretch if possible; the production calendar is the honest constraint.