Guangdong Chair Factory Notes Production floor, Longjiang · Foshan

Factory Notes › Wooden Bar Stools

Line Capacity: How Many Bar Stools a Day, and What Limits It

Why daily output for bar stools depends on the model mix, the season and the bottleneck - and how dates are planned from that.

Updated 2026-11-07Longjiang, Foshan11 min read

Why daily output for bar stools depends on the model mix, the season and the bottleneck - and how dates are planned from that.

These notes come off the production floor in Longjiang, Foshan. The current wooden bar stools supplier range is on the main site, with a specification page for every model in it.

Capacity is a model-mix question

The honest answer to "how many bar stool a day" is "of which model". A simple frame runs fast; an upholstered bar stool with a deep finish takes the same bench hours as two simple ones. Quotations are planned against the mix, not against an average.

Stools pack small — 0.08 to 0.12 m³ for two — so the freight per piece is the best in the catalogue and a 40HC holds a lot of them. MOQ is 6 pieces per model.

What the mix looks like right now

The catalogue lists 86 models in this category: 44% on a solid or wood frame and 33% with an upholstered or soft cover.

The most common order quantity in this category is 6 pcs (36 models ship at that level).

FactorEffectPlanning note
Model complexityFrame vs upholsteredSets bench hours
Finish systemCoat countBooth time per piece
SeasonCNY and peaksLead time +/- weeks
MixSimple vs detailed bar stoolsBottleneck location
SurgeOvertime, quotedNever free

Capacity factors

The bottleneck moves with the order

Finishing and upholstery are the usual limits; a plain-frame bar stool run is limited by machining instead. Knowing where the bottleneck sits is how a promised date is built.

The column is turned or machined from a single blank wherever the model allows, because a jointed column on a high stool is a wobble waiting to happen. On swivel models the mount plate is machined to fit the tube rather than welded to a rough cut.

Seasonality is real

Pre-Chinese-New-Year months run at full stretch and lead times stretch with them; post-holiday months have slack. Buyers who plan around the calendar get better dates than buyers who plan around hope.

Stools pack small — 0.08 to 0.12 m³ for two — so the freight per piece is the best in the catalogue and a 40HC holds a lot of them. MOQ is 6 pieces per model.

What surge capacity actually costs

Yes, the line can sprint - with overtime and with finish quality held by inspection rather than by schedule. It is available, it is quoted, and it is never free.

Beyond the frame test a stool gets a stability check at height and a footring load test: push the ring sideways with the stool loaded and it must not deform. Swivel models are cycled, not just sat on.

Questions

What is your daily output for bar stools?

It depends on the model mix; quotations carry a production plan with the bottleneck named, not a round number.

Can you hold a peak-season date?

Dates are promised against the calendar, not against hope - peak-season orders are booked with the stretch priced in.

Why did my simple model run late?

If the mix that week was upholstery-heavy, the simple frames queue behind the booth. The plan, not the promise, is what to read.

How early should I book a big wooden bar stools order?

Ahead of the pre-holiday stretch if possible; the production calendar is the honest constraint.