Lead Times and Production Planning for Lounge Chairs

Where the 25 to 40 days actually go on a lounge chair order, what Chinese New Year does to the schedule, and how to compress it honestly.

Updated 2026-11-14Longjiang, Foshan16 min read

Where the 25 to 40 days actually go on a lounge chair order, what Chinese New Year does to the schedule, and how to compress it honestly.

These notes come off the production floor in Longjiang, Foshan. The current wooden lounge chairs range is on the main site, with a specification page for every model in it.

Where the 25 to 40 days go

Material preparation, machining, assembly, finishing and curing, upholstery, packing, and booking. The variable part is finishing: every extra coat adds a day of curing, and a water-based system adds more.

The fixed part is the queue. A line running three shifts cannot insert a new model without a fixture change, which is why a confirmed order has a slot and an enquiry does not.

Samples first

A prototype on an existing fixture takes 7 to 15 days. A new geometry with new tooling takes longer. Air freight is the buyer's cost and worth paying: approving from photographs is how specifications drift. Wooden Lounge Chairs can usually be sampled against an existing fixture.

StageDurationNotes
Enquiry to quotation1-2 daysFeasibility and pricing
Sample7-15 daysExisting fixture; longer with tooling
Material preparation3-5 daysTimber, board, fabric, hardware
Production18-25 daysMachining through packing
Booking and loading3-5 daysVessel, documents, loading photographs

Timeline

Seasonality

Chinese New Year shuts production for two to three weeks and the month before it is the busiest of the year. An order confirmed in December does not ship before March. Autumn is the next tightest window because European and North American buyers are restocking at the same time.

How to compress a schedule honestly

Confirm the specification in one pass rather than three. Approve the sample quickly. Use a stock finish. Avoid a tooling change if a near-equivalent fixture exists. Book the vessel while the run is finishing, not after.

What does not work is asking for a shorter lead time on the same specification. The days are in the curing and the clamp time; they are physics, not scheduling.

What actually delays an order

In order of frequency: the specification changed after production started; the sample approval took three weeks; the finish needed a second colour round; the covering was out of stock at the mill; and the vessel was full. Production itself is rarely the cause.

Four of those five are on the buyer's side of the fence and all five are avoidable with a decision made early. The most useful thing a buyer can do for a schedule is approve the sample the day it arrives.

Booking the vessel

Space is booked while the run is finishing, not after. Peak season sailings fill and a container that misses one is on the next, which is a week. We book against the loading plan issued with the quotation so the number booked matches the number loaded.

Transhipment versus direct matters more than the saving suggests: a direct sailing costs more and arrives predictably, a transhipped one saves money and adds a variable week at the hub.

How we handle a delay

By telling you before the date rather than on it. A schedule slip discovered at machining can be recovered with overtime or a batch change; the same slip discovered in the last week cannot.

Any factory that has run long enough has slipped at some point. The difference is whether you hear it from them or from the tracking.

Bought-in material lead times

Timber, board and hardware are held in stock. Covering is not: a specific fabric or leather is ordered from the mill, which is the single most common cause of a schedule slipping on an upholstered order. Confirming the cover at the same time as the frame is the cheapest schedule insurance there is.

If the covering is a stock item at the mill it is a week; if it is a mill run to your colour it is three to five.

Ramp-up on a new model

The first production run of a new model is slower than the second: fixtures settle, operators learn the assembly sequence, and the finish colour usually needs one adjustment. Budget for it in the schedule rather than discovering it in week three.

This is also why the sample matters so much to the timeline. A sample approved with the production method in mind goes into production without a second round.

Planning backwards

Take the opening date, subtract shipping, subtract two weeks of buffer, subtract production, subtract sampling, and you have the date the enquiry should have been sent. Most missed openings were missed at that step, not in production.

Questions

How long is the lead time?

25 to 40 days from deposit depending on finish and season, plus 7 to 15 days for a sample.

When should I order for a spring opening?

Work backwards from the opening date and add two weeks. Avoid confirming in December - Chinese New Year closes production for two to three weeks.

Can you expedite?

Only by simplifying the specification: stock finish, existing fixture, quick sample approval. Curing and clamp times cannot be compressed.